4 Mat-Weavers can Weave 4 Mats in 4 Days. At the Same Rate How Many Mats would be Woven by 8 Mat-Weavers in 8...

4 mat-weavers can weave 4 mats in 4 days. Mats woven by 8 mat-weavers in 8 days can be figure out in this way. Explanation Solution Explanation Three given...

2 Men and 7 Boys can do a Piece of Work in 14 Days; 3 Men and 8 Boys can do the Same in...

2 men and 7 boys can do a piece of work in 14 days. 3 men and 8 boys can do the same in 11...

If 3 Men or 6 Boys can Do a Piece of Work in 10 Days Working 7 Hours a Day; How Many Days will...

If 3 men or 6 boys can do a piece of work in 10 days working 7 hours a day. Days required by 6 men...

15 Men Take 21 Days of 8 Hours Each to Do a Piece of Work. How Many Days of 6 Hours Each would 21...

15 men take 21 days of 8 hours each to do a piece of work. 3 women do as much work as 2 men. Days required...

A Garrison of 500 Men had Provisions for 27 Days. After 3 Days a Reinforcement of 300 Men Arrived. For How Many More Days...

A garrison of 500 men had provisions for 27 days. After 3 days a reinforcement of 300 men arrived. Total days the remaining food would last...