- 12 men working 8 hours per day complete a piece of work in 18 days.
- Hours in a day for 15 men to complete the same work in 12 days can be figure out in this way.
Explanation
Three given entities here are
- Men
- Days
- Hours
To determine the relation here, let suppose; Hours in a day for 15 men to complete the same work in 12 days = y
Case I
Men Hours
12 8
15 y
- Lesser men mean more hours in a day are required to finish the job.
- More men mean less hours in a day to finish the given job.
This clearly indicates that there is inverse relation.
Direct/Indirect relation tells how the equation will be written.
12 : 15 :: y : 8 ________ (i)
Case II
Days Hours
18 8
12 y
- More days mean less hours.
- Less days mean more hours.
This clearly indicates that there is inverse relation.
Direct/Indirect relation tells how the equation will be written.
18 : 12 :: y : 8 ________ (ii)
By (i) and (ii)
12 : 15 :: y : 8
18 : 12
12 x 18 x 8 = 15 x 12 x y ________ (A)
After simplifying equation (A), we can easily figure out the value of y (y = 9.6 hours)
To Find
Hours in a day for 15 men to complete the same work in 12 days = ?
Solution
Method I
Let suppose
Hours in a day for 15 men to complete the same work in 12 days = y
Men Days Hours
12 18 8
15 12 y
- Relation between men and hours is inverse.
- Relation between days and hours is also inverse so;
12 : 15 :: y : 8
18 : 12
12 x 18 x 8 = 15 x 12 x y
1728 = 180y
1728/180 = y
y = 9.6
Hours in a day for 15 men to complete the same work in 12 days = 9.6 hours answer
Method II
Hours in 18 day for 12 men to complete the work = 8 hours
Hours in 18 days for 1 man to complete the work = (8 x 12) hours
Hours in a day for 1 man to complete the work = (8 x 12 x 18) hours
Hours in 12 days for 1 man to complete the work = (8 x 12 x 18)/12 hours
Hours in 12 days for 15 men to complete the work = (8 x 12 x 18)/(12 x 15) hours
Hours in 12 days for 15 men to complete the work = 1728/180 hours
Hours in 12 days for 15 men to complete the work = 9.6 hours
Hours in a day for 15 men to complete the same work in 12 days = 9.6 hours answer
Conclusion